SR30 over Bessemer

Bridges
owner
PennDot District 11
customer
Brayman Construction
location
Allegheny County, PA
product
Deck Modules, Abutments, Approach Slab, Sleeper Slabs and Wingwalls

SCOPE

  • Lightweight concrete Deck Modules cast with integral steel beams, 4 Modules weighing approximately 30 tons and 2 outer Modules with barrier weights approximately 50 tons.
  • Deck Modules and Approach Slabs were all carefully match-cast.
  • 28 Precast bridge components, weighing a combined 575 tons, were pre-assembled in the yard to ensure proper fit in the field.
  • 56 LF bridge was erected in 57 hours through the use of Accelerated Bridge Construction methods with minimal disruption to the urban community.